GLOBAL PROJECT DELIVERY

MENA · Africa · Central Asia · Europe · Americas

Direct investor desk ↗
SEVEN CAPITAL GATES

The client owns a decision package at every phase.

Inputs, activities, deliverables, responsibilities and approval criteria are controlled before the next capital commitment.

01

Investment Definition & Feasibility

Client input: investment objective, destination and available site data.

Infinity activity: demand, capacity, site, CAPEX/OPEX and risk assessment.

Decision gate: proceed, redefine or stop.
02

Clinical, Process & Concept Design

Input: approved scope and capacity.

Activity: programme, workflow, adjacency, concept layout and URS.

Gate: approve the design basis.
03

Detailed Engineering & Infrastructure

Input: frozen concept and survey data.

Activity: architecture, MEP, HVAC, utilities, gases, power and waste coordination.

Gate: release coordinated design for procurement/construction.
04

Procurement & Technology Integration

Input: approved specifications and budget.

Activity: vendor evaluation, packages, FAT, logistics and responsibility assignment.

Gate: authorise long-lead commitments.
05

Quality & Regulatory Readiness

Input: intended market, legal operator and product/service scope.

Activity: QMS, validation master plan, licensing roadmap and gap closure.

Gate: accept the readiness plan and legal responsibilities.
06

Installation, Commissioning & Qualification

Input: released site, equipment and protocols.

Activity: SAT, calibration, commissioning, IQ/OQ where applicable and punch-list closure.

Gate: provisional acceptance.
07

Training, Pilot Operation & Handover

Input: qualified systems and recruited operator team.

Activity: training, simulation/pilot, performance review and controlled handover.

Gate: operational handover and support plan.
ILLUSTRATIVE RESPONSIBILITY MATRIX

One project, clearly separated responsibilities.

Investor / Client — accountable for investment, approvals and owner decisionsInfinity IVD — responsible for contracted integration and project outputsLocal Architect / Contractor — responsible for licensed local design and construction scopeEquipment OEM — responsible for compliant equipment, FAT and technical recordsTechnology Owner — accountable for licensed know-how and transfer boundariesAuthority / Certification Body — independently decides licences and certificationsFuture Operator — responsible for recruitment, operation and sustained compliance

RACI is customised in the contract. Design freeze, change control, FAT, SAT, qualification, punch-list closure, provisional acceptance, final acceptance and warranty handover are defined as controlled milestones.

Project desk