Investment Definition & Feasibility
Client input: investment objective, destination and available site data.
Infinity activity: demand, capacity, site, CAPEX/OPEX and risk assessment.
Decision gate: proceed, redefine or stop.Inputs, activities, deliverables, responsibilities and approval criteria are controlled before the next capital commitment.
Client input: investment objective, destination and available site data.
Infinity activity: demand, capacity, site, CAPEX/OPEX and risk assessment.
Decision gate: proceed, redefine or stop.Input: approved scope and capacity.
Activity: programme, workflow, adjacency, concept layout and URS.
Gate: approve the design basis.Input: frozen concept and survey data.
Activity: architecture, MEP, HVAC, utilities, gases, power and waste coordination.
Gate: release coordinated design for procurement/construction.Input: approved specifications and budget.
Activity: vendor evaluation, packages, FAT, logistics and responsibility assignment.
Gate: authorise long-lead commitments.Input: intended market, legal operator and product/service scope.
Activity: QMS, validation master plan, licensing roadmap and gap closure.
Gate: accept the readiness plan and legal responsibilities.Input: released site, equipment and protocols.
Activity: SAT, calibration, commissioning, IQ/OQ where applicable and punch-list closure.
Gate: provisional acceptance.Input: qualified systems and recruited operator team.
Activity: training, simulation/pilot, performance review and controlled handover.
Gate: operational handover and support plan.RACI is customised in the contract. Design freeze, change control, FAT, SAT, qualification, punch-list closure, provisional acceptance, final acceptance and warranty handover are defined as controlled milestones.